MAINPORT CONVERSION

download PDF for this project

Mainport AshIn the Mainport Conversion Project, Maritime Management sourced, pre-purchased, inspected, made conversion design and drydock specification, executed the drydock work, class and stability work – all in-house with our own recourses.





Jan Christian Berg - Managing Director


Ships

Client

Ship Type

Job Category

-

-

-

-

Mainport Elm, Mainport Ash, Mainport Oak

Mainport Holding

Seismic Support Vessel

Consultancy / Conversion



Jan Christian Berg - Managing Director



The 3 ships were Anchor Handling Vessels and they were converted to Seismic Support Vessels.

  • MV Mainport Elm
    Conversion at Sunderland, UK November 2007 – January 2008. Seismic Support Vessel from AHTS including, tanks, equipment and accommodation.

  • MV Mainport Ash
    Conversion at Istanbul, Turkey August - September 2007. Seismic Support Vessel from AHTS including, tanks, equipment and accommodation.

  • MV Mainport Oak
    Conversion at Cape Town, RSA June – July 2007. Seismic Support Vessel from AHTS including, tanks, equipment and accommodation.


Jan Christian Berg - Managing Director


Mainport ConversionThe job included the computer modelling of the vessels to recalculate ship stability and issue new Stability booklets.

The major conversion also meant extensive liaising with Class who had to approve project designs as well as other works.

For each ship the job was different but basically the passenger capacity was brought up to about 40 and tanks were increased to allow for offshore bunkering of the mother vessel.

New equipment was purchased and installed for the specific trade in mind.

Owner was continuously informed of progress at all stages in the purchase inspection, acquisition, design and conversion process, both on the technical and commercial aspects.